CUP: H42G20000890001
OPERE EFFICIENTAMENTO ENERGETICO E MANUTENZIONE STRAORDINARIA PRESSO SUOLA DELL'INFANZIA DI CASTELLETTO DI LENO
SUMMARY OF THE PROJECT
POSA IN OPERA RIVESTIMENTO A CAPPOTTO, INSTALLAZIONE IMPIANTO FOTOVOLTAICO, SOSTITUZIONE SERRAMENT
Implementation indicator
Spesa pubblica pagata totale
- Target
- 90,000 euro
- Achieved
- 89,404.08 euro
Download project
Funding monitored
€ 89,404.08
of which cohesion funds
€ 89,404.08
Given name | Amount |
---|---|
Development and Cohesion Fund | 89404.08 |
- Economies:
- € 595.92
Payments monitored
€ 89,404.08
of which cohesion funds
€ 89,404.08
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 89404.08 | 89404.08 | 100 |
State of progress
Completed
Expected start: 16/07/2020
Effective start: 16/07/2020
Expected end: 31/08/2020
Effective end: 02/10/2020
Entities
- Planning body
- COMUNE DI LENO
- Beneficiary
- COMUNE DI LENO
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 89,404.08
- Payments on cohesion funds
- € 89,404.08
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile