EFFICIENTAMENTO ENERGETICO MUNICIPIO ATTRAVERSO LA SOSTITUZIONE DEI SERRAMENTI ESTERNI
SUMMARY OF THE PROJECT
Sostituzione serramenti presso municipio
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 100 KWh/a
- Achieved
- -
Download project
Funding monitored
€ 50,000.00
of which cohesion funds
€ 50,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 50000.00 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 15/11/2020
Effective start: 13/11/2020
Expected end: 30/06/2021
Effective end: not available
Entities
- Planning body
- COMUNE DI LA THUILE
- Implementing body
- COMUNE DI LA THUILE
- Beneficiary
- COMUNE DI LA THUILE
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 50,000.00
- Payments on cohesion funds
- € 0.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile