CUP: C62J19000440001
LAVORI DI SOSTITUZIONE DELLE TORRI FARO DELL'IMPIANTO SPORTIVO PIETRO SECCI
SUMMARY OF THE PROJECT
EFFICIENTAMENTO ENERGETICO
Implementation indicator
Riduzione annuale del consumo di energia
- Target
- 15.10 MW
- Achieved
- 15.10 MW
Download project
Funding monitored
€ 64,250.79
of which cohesion funds
€ 64,250.79
Given name | Amount |
---|---|
Development and Cohesion Fund | 64250.79 |
- Economies:
- € 25,749.21
Payments monitored
€ 63,192.94
of which cohesion funds
€ 63,192.94
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 60979.60 | 60979.60 | 94 |
2021 | 2213.34 | 63192.94 | 98 |
State of progress
Completed
Expected start: 29/10/2019
Effective start: 29/10/2019
Expected end: 23/04/2021
Effective end: 23/04/2021
Entities
- Planning body
- COMUNE DI LA MADDALENA
- Beneficiary
- COMUNE DI LA MADDALENA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
Same type of investment
EFFICIENTAMENTO ENERGETICO - LAMPIONI PIAZZA COMANDO (ANNUALITÃ 2023) | € 86,266 |