CUP: D83J21000180001
FONDO DI SOSTEGNO ALLE ATTIVITA' PRODUTTIVE
SUMMARY OF THE PROJECT
CONTRIBUTI A FONDO PERDUTO
Implementation indicator
Spesa pubblica pagata totale
- Target
- 903.74 euro
- Achieved
- 903.74 euro
Download project
Funding monitored
€ 903.74
of which cohesion funds
€ 903.74
Given name | Amount |
---|---|
Development and Cohesion Fund | 903.74 |
Payments monitored
€ 903.74
of which cohesion funds
€ 903.74
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2022 | 903.74 | 903.74 | 100 |
State of progress
Completed
Expected start: 29/08/2022
Effective start: 30/08/2022
Expected end: 30/08/2022
Effective end: 30/08/2022
Entities
- Planning body
- COMUNE DI FRONTONE
- Beneficiary
- COMUNE DI FRONTONE
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 903.74
- Payments on cohesion funds
- € 903.74
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile