INTERVENTO STRAORDINARIO PER L'EFFICIENTAMENTO ENERGETICO DELLA PUBBLICA ILLUMINAZIONE IN VIA S. ALLENDE E VIA STAZIONE
SUMMARY OF THE PROJECT
MANUTENZIONE STRAORDINARIA DI EFFICIENTAMENTO ENERGETICO DI PUBBLICA ILLUMINAZIONE
Implementation indicator
Punti illuminanti/luce
- Target
- 22 num
- Achieved
- 22 num
Download project
Funding monitored
€ 59,398.75
of which cohesion funds
€ 50,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 50000.00 |
Municipality | 9398.75 |
- Economies:
- € 3,601.25
Payments monitored
€ 55,876.75
of which cohesion funds
€ 50,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 55876.75 | 55876.75 | 94 |
State of progress
Open
Expected start: 30/10/2019
Effective start: 30/10/2019
Expected end: 14/02/2020
Effective end: 14/02/2020
Entities
- Planning body
- COMUNE DI FOSSATO DI VICO
- Beneficiary
- COMUNE DI FOSSATO DI VICO
- Executor
-
TSP ENGINEERING SRL
IMPIANTI ELETTRICI S.A.S. DI FISCHI PASQUALE LUZZI PINO
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 50,000.00
- Payments on cohesion funds
- € 50,000.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
ATTIVITA DI ASSISTENZA TECNICA E DI GESTIONE, MONITORAGGIO E VALUTAZIONE DELLA STRATEGIA AREA INTERNA. GESTIONE, MONITORAGGIO E VALUTAZIONE. | € 202,000 |
Same type of investment