Lavori di installazione impianto fotovoltaico su copertura mensa in loc. Pian del Gac'
SUMMARY OF THE PROJECT
Installazione di un impianto fotovoltaico sulla copertura della mensa in loc. Pian del Gac' a Fornace (TN)
Implementation indicator
Potenza installata
- Target
- 15 KW
- Achieved
- 16.80 KW
Download project
Funding monitored
€ 89,094.39
of which cohesion funds
€ 50,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 50000.00 |
Province | 39094.39 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 31/10/2019
Effective start: 31/10/2019
Expected end: 29/12/2019
Effective end: 07/05/2020
Entities
- Planning body
- COMUNE DI FORNACE
- Beneficiary
- COMUNE DI FORNACE
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 50,000.00
- Payments on cohesion funds
- € 0.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
Nuovo impianto fotovoltaico | € 74,360 |