CUP: I81C19000080001
013/LP
SUMMARY OF THE PROJECT
RELAMPING
Implementation indicator
Riduzione dei consumi annui di energia elettrica per illuminazione pubblica
- Target
- 1,920.95 GWh
- Achieved
- 1,920.95 GWh
Download project
Funding monitored
€ 48,581.94
of which cohesion funds
€ 48,581.94
Given name | Amount |
---|---|
Development and Cohesion Fund | 48581.94 |
- Economies:
- € 1,418.06
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Not started
Expected start: 31/10/2019
Effective start: 31/10/2019
Expected end: 30/12/2019
Effective end: 04/02/2020
Entities
- Planning body
- COMUNE DI FEROLETO DELLA CHIESA
- Beneficiary
- COMUNE DI FEROLETO DELLA CHIESA
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 48,581.94
- Payments on cohesion funds
- € 0.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile