CUP: F61B19000280001
INTERVENTI VOLTI ALL'EFFICIENTAMENTO ENERGETICO ANNO 2019
SUMMARY OF THE PROJECT
INTERVENTI VOLTI ALL'EFFICIENTAMENTO ENERGETICO
Implementation indicator
Riduzione annuale del consumo di energia
- Target
- 1.40 MW
- Achieved
- 1.49 MW
Funding monitored
€ 129,994.73
of which cohesion funds
€ 129,994.73
Given name | Amount |
---|---|
Development and Cohesion Fund | 129994.73 |
- Economies:
- € 5.27
Payments monitored
€ 129,994.73
of which cohesion funds
€ 129,994.73
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 113357.01 | 113357.01 | 87 |
2021 | 16637.72 | 129994.73 | 100 |
State of progress
Completed
Expected start: 30/10/2019
Effective start: 30/10/2019
Expected end: 09/12/2019
Effective end: 03/01/2020
Entities
- Planning body
- COMUNE DI FERMO
- Beneficiary
- COMUNE DI FERMO
- Executor
- G.R. DI RAMAIOLI DOMENICO & C. SNC
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile