CUP: E59G19000250005
MANUTENZIONE STRAORDINARIA E MESSA IN SICUREZZA DEL CIMITERO COMUNALE - I STRALCIO
SUMMARY OF THE PROJECT
Interventi che mirani alla messa in sicurezza e al miglioramento delle condizioni in cui versa il cimitero di Erice
Implementation indicator
Superficie oggetto di intervento
- Target
- 600 mq
- Achieved
- 600 mq
Download project
Funding monitored
€ 108,962.10
of which cohesion funds
€ 108,962.10
Given name | Amount |
---|---|
Another public source | 108962.10 |
- Economies:
- € 21,037.90
Payments monitored
€ 98,730.40
of which cohesion funds
€ 98,730.40
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 5200.00 | 5200.00 | 4 |
2020 | 93530.40 | 98730.40 | 90 |
State of progress
Open
Expected start: 25/11/2019
Effective start: 25/11/2019
Expected end: 22/02/2020
Effective end: 15/09/2020
Entities
- Planning body
- COMUNE DI ERICE
- Implementing body
- COMUNE DI ERICE
- Beneficiary
- COMUNE DI ERICE
- Executor
- Studio Due Costruzioni di Poma Girolamo
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 108,962.10
- Payments on cohesion funds
- € 98,730.40
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile