CUP: E62G19000320005
OPERE DI RISANAMENTO CONSERVATIVO FINALIZZATE AL RISPARMIO ENERGETICO DELLA SALA POLIVALENTE DI VIA DON PIETRO RIGOLI DA ADIBIRE A BIBLIOTECA
SUMMARY OF THE PROJECT
OPERE DI RISANAMENTO CONSERVATIVO FINALIZZATE AL RISPARMIO ENERGETICO DELLA SALA POLIVALENTE DI VIA DON PIETRO RIGOLI DA ADIBIRE A BIBLIOTECA
Implementation indicator
Numero edifici scolastici oggetto dell'intervento
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 50,363.51
of which cohesion funds
€ 50,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 50000.00 |
Municipality | 363.51 |
- Economies:
- € 636.49
Payments monitored
€ 50,363.51
of which cohesion funds
€ 50,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 50363.51 | 50363.51 | 100 |
State of progress
Completed
Expected start: 13/01/2020
Effective start: 13/01/2020
Expected end: 30/05/2020
Effective end: 29/05/2020
Entities
- Planning body
- COMUNE DI DOSSENA
- Beneficiary
- COMUNE DI DOSSENA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile