CUP: B46E19000540001
SISTEMAZIONE PARCO
SUMMARY OF THE PROJECT
SISTEMAZIONE PARCO , PIANTE , SIEPI E TAPPETO ERBOSO
Implementation indicator
Spazi aperti creati o ripristinati in aree urbane
- Target
- 1,600 mq
- Achieved
- 1,600 mq
Download project
Funding monitored
€ 14,640.00
of which cohesion funds
€ 14,640.00
Given name | Amount |
---|---|
Another public source | 14640.00 |
Payments monitored
€ 14,640.00
of which cohesion funds
€ 14,640.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 14640.00 | 14640.00 | 100 |
State of progress
Completed
Expected start: 28/10/2019
Effective start: 09/12/2019
Expected end: 28/02/2020
Effective end: 11/02/2020
Entities
- Planning body
- COMUNE DI CRESSA
- Beneficiary
- COMUNE DI CRESSA
- Executor
- COMUNE DI CRESSA
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 14,640.00
- Payments on cohesion funds
- € 14,640.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same type of investment
banda Ultralarga nelle aree bianche del territorio della Regione Piemonte con FONDI FSC | € 53,745,935 |
INSTALLAZIONE NUOVI PUNTI LUCE DELLA PUBBLICA ILLUMINAZIONE | € 5,118 |