CUP: I41E20000250001
LAVORI DI MESSA IN SICUREZZA E EFFICIENTAMENTO DELL'IMPIANTO DI ILLUMINAZIONE PUBBLICA IN VIA FORCELLA, PIAZZA G. FINITI E VIA FONTECERRO S.P. 45/F
SUMMARY OF THE PROJECT
MESSA IN SICUREZZA E EFFICIENTAMENTO ENERGETICO IMPIANTI DI PUBBLICA ILLUMINAZIONE
Implementation indicator
Punti illuminanti/luce
- Target
- 17 num
- Achieved
- 17 num
Funding monitored
€ 18,506.82
of which cohesion funds
€ 18,506.82
Given name | Amount |
---|---|
Development and Cohesion Fund | 18506.82 |
- Economies:
- € 823.07
Payments monitored
€ 18,371.41
of which cohesion funds
€ 18,371.41
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 18371.41 | 18371.41 | 99 |
State of progress
Completed
Expected start: 13/11/2020
Effective start: 13/11/2020
Expected end: 11/02/2021
Effective end: 07/01/2021
Entities
- Planning body
- COMUNE DI COTTANELLO
- Beneficiary
- COMUNE DI COTTANELLO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile