CUP: C87H19001430001
MESSA IN SICUREZZA PATRIMONIO COMUNALE
SUMMARY OF THE PROJECT
PERCORSI PEDONALI
Implementation indicator
Spesa pubblica ammessa totale
- Target
- 50,000 euro
- Achieved
- 47,886.46 euro
Funding monitored
€ 47,886.46
of which cohesion funds
€ 47,886.46
Given name | Amount |
---|---|
Development and Cohesion Fund | 47886.46 |
- Economies:
- € 2,113.54
Payments monitored
€ 46,783.78
of which cohesion funds
€ 46,783.78
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 46783.78 | 46783.78 | 97 |
State of progress
Completed
Expected start: 31/10/2019
Effective start: 31/10/2019
Expected end: 29/01/2020
Effective end: 26/06/2020
Entities
- Planning body
- COMUNE DI COSTIGLIOLE SALUZZO
- Beneficiary
- COMUNE DI COSTIGLIOLE SALUZZO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
POTENZIAMENTO COLLEGAMENTI MERCI TORINO-SAVONA/FOSSANO-CUNEO/CUNEO-BUSCA E AREA LOGISTICA | € 10,000,000 |