CUP: E32J19001960005
RIQUALIFICAZIONE DELLA CENTRALE TERMICA PRESSO COMUNE COSTAFORUM AI FINI DELL EFFICIENTAMENTO ENERGETICO DELL IMMOBILE VIA XXV APRILE SEDE COMUNALE EFFICIENTAMENTO ENERGETICO DELL IMMOBILE
SUMMARY OF THE PROJECT
RIQUALIFICAZIONE DELLA CENTRALE TERMICA PRESSO COMUNE COSTAFORUM AI FINI DELL EFFICIENTAMENTO ENERGETICO DELL IMMOBILE VIA XXV APRILE SEDE COMUNALE EFFICIENTAMENTO ENERGETICO DELL IMMOBILE
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 100 KWh/a
- Achieved
- 100 KWh/a
Download project
Funding monitored
€ 61,388.80
of which cohesion funds
€ 50,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 50000.00 |
Municipality | 11388.80 |
Payments monitored
€ 60,104.29
of which cohesion funds
€ 50,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 50024.06 | 50024.06 | 81 |
2020 | 10080.23 | 60104.29 | 97 |
State of progress
Completed
Expected start: 09/09/2019
Effective start: 09/09/2019
Expected end: 09/11/2019
Effective end: 20/12/2019
Entities
- Planning body
- COMUNE DI COSTA MASNAGA
- Implementing body
- COMUNE DI COSTA MASNAGA
- Beneficiary
- COMUNE DI COSTA MASNAGA
- Executor
- COMUNE DI COSTA MASNAGA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile