CUP: G42J19000550001
LAVORI DI EFFICIENTAMENTO ENERGETICO DELLA CENTRALE TERMICA DELLA PISCINA COMUNALE DI CORREGGIO
SUMMARY OF THE PROJECT
INSTALLAZIONE DI NUOVO GENERATORE A CONDENSAZIONE E AMPLIAMENTO ACCUMULO IMPIANTO SOLARE-TERMICO
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 80,995 KWh/a
- Achieved
- 80,995 KWh/a
Funding monitored
€ 70,728.68
of which cohesion funds
€ 70,728.68
Given name | Amount |
---|---|
Development and Cohesion Fund | 70728.68 |
Payments monitored
€ 70,728.68
of which cohesion funds
€ 70,728.68
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 70728.68 | 70728.68 | 100 |
State of progress
Completed
Expected start: 23/08/2019
Effective start: 23/08/2019
Expected end: 30/09/2019
Effective end: 27/09/2019
Entities
- Planning body
- COMUNE DI CORREGGIO
- Beneficiary
- COMUNE DI CORREGGIO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile