CUP: J52G19000240005
EFFICIENTAMENTO ENERGETICO DELLA SCUOLA PRIMARIA
SUMMARY OF THE PROJECT
LAVORI IMPIANTO TERMICO
Implementation indicator
Numero edifici scolastici oggetto dell'intervento
- Target
- 1 num
- Achieved
- 1 num
Funding monitored
€ 75,968.92
of which cohesion funds
€ 50,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 50000.00 |
Municipality | 25968.92 |
- Economies:
- € 31.08
Payments monitored
€ 75,968.92
of which cohesion funds
€ 50,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 75968.92 | 75968.92 | 100 |
State of progress
Completed
Expected start: 10/10/2019
Effective start: 10/10/2019
Expected end: 09/11/2019
Effective end: 09/11/2019
Entities
- Planning body
- COMUNE DI CIGOLE
- Beneficiary
- COMUNE DI CIGOLE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile