CUP: J42J19001410001
Lavori efficientamento biblioteca
SUMMARY OF THE PROJECT
lavori efficientamento biblioteca
Implementation indicator
Punti illuminanti/luce
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 22,692.00
of which cohesion funds
€ 22,692.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 22692.00 |
Payments monitored
€ 22,692.00
of which cohesion funds
€ 22,692.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 22692.00 | 22692.00 | 100 |
State of progress
Completed
Expected start: 31/10/2019
Effective start: 29/10/2019
Expected end: 30/05/2020
Effective end: 30/05/2020
Entities
- Planning body
- COMUNE DI CHIGNOLO D'ISOLA
- Beneficiary
- COMUNE DI CHIGNOLO D'ISOLA
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 22,692.00
- Payments on cohesion funds
- € 22,692.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
LAVORI DI RIQUALIFICAZIONE ENERGETICA DEL SISTEMA DI ILLUMINAZIONE A LED E DI EMERGENZA DELLA SEDE COMUNALE | € 24,400 |
condizionatori uffici | € 1,920 |
Same type of investment
LAVORI DI RIQUALIFICAZIONE ENERGETICA DEL SISTEMA DI ILLUMINAZIONE A LED E DI EMERGENZA DELLA SEDE COMUNALE | € 24,400 |
condizionatori uffici | € 1,920 |