CUP: F17H19002350001
Lavori di messa in sicurezza aree e viabilità comunale nel Comune di Cerva
SUMMARY OF THE PROJECT
messa in sicurezza aree e viabilità comunali
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1 km
- Achieved
- 1 km
Download project
Funding monitored
€ 48,332.96
of which cohesion funds
€ 48,332.96
Given name | Amount |
---|---|
Development and Cohesion Fund | 48332.96 |
- Economies:
- € 1,667.04
Payments monitored
€ 24,370.79
of which cohesion funds
€ 24,370.79
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 24370.79 | 24370.79 | 50 |
State of progress
Open
Expected start: 28/10/2019
Effective start: 31/10/2019
Expected end: 26/11/2019
Effective end: 11/07/2020
Entities
- Planning body
- COMUNE DI CERVA
- Implementing body
- COMUNE DI CERVA
- Beneficiary
- COMUNE DI CERVA
- Executor
- COMUNE DI CERVA
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 48,332.96
- Payments on cohesion funds
- € 24,370.79
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
LA VIA DEL MARE, DELLOLIO E DELLE MINORANZELINGUISTICHE | € 2,000,000 |
Cerva - INTERVENTO DI MESSA IN SICUREZZA DELLA VIABILITA COMUNALE | € 57,143 |