CUP: B77H19002820005
Fornitura e posa di barriere stradali come manutenzione straordinaria nonchè misure di sicurezza della rete viaria
SUMMARY OF THE PROJECT
Fornitura e posa di barriere stradali come manutenzione straordinaria per la messa in sicurezza della rete viaria comunale
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 0.80 km
- Achieved
- -
Download project
Funding monitored
€ 48,611.63
of which cohesion funds
€ 48,611.63
Given name | Amount |
---|---|
Development and Cohesion Fund | 41267.78 |
Municipality | 7343.85 |
Payments monitored
€ 47,951.73
of which cohesion funds
€ 47,951.73
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 47951.73 | 47951.73 | 98 |
State of progress
Settled
Expected start: 09/10/2019
Effective start: 09/10/2019
Expected end: 31/10/2020
Effective end: not available
Entities
- Planning body
- COMUNE DI CASTELROTTO
- Beneficiary
- COMUNE DI CASTELROTTO
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 48,611.63
- Payments on cohesion funds
- € 47,951.73
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile