CUP: H22G19000170005
LAVORI INERENTI L'EFFICIENTAMENTO ENERGETICO DEI SEGUENTI EDIFICI: MUNICIPIO, SCUOLA PRIMARIA DI VIA GIOVENZANA E PALAZZINA COMUNALE DI VIA GARIBALDI
SUMMARY OF THE PROJECT
SOSTITUZIONE DEI GENERATORI DI CALORE CON DUE NUOVI GENERATORI DI CALORE DI NUOVA GENERAZIONE, SOSTITUZIONE DI TUTTE LE ELETTROPOMPE E ADEGUAMENTO IMPIANTO ELETTRICO
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 66,376.50 KWh/a
- Achieved
- 66,376.50 KWh/a
Funding monitored
€ 109,396.66
of which cohesion funds
€ 90,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 90000.00 |
Municipality | 19396.66 |
- Economies:
- € 27,753.39
Payments monitored
€ 108,492.74
of which cohesion funds
€ 90,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 102034.62 | 102034.62 | 93 |
2020 | 6458.12 | 108492.74 | 99 |
State of progress
Completed
Expected start: 23/08/2019
Effective start: 23/08/2019
Expected end: 05/10/2019
Effective end: 04/10/2019
Entities
- Planning body
- COMUNE DI CASATENOVO
- Beneficiary
- COMUNE DI CASATENOVO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile