CUP: J22J19000790001
EFFICIENTAMENTO ENERGETICO DEL MUNICIPIO
SUMMARY OF THE PROJECT
NUOVA CALDAIA A CONDENZAZIONE E NUOVI SPLIT PRESSO MUNICIPIO
Implementation indicator
Numero di edifici pubblici con classificazione del consumo energetico migliorata
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 25,458.96
of which cohesion funds
€ 25,458.96
Given name | Amount |
---|---|
Development and Cohesion Fund | 25458.96 |
Payments monitored
€ 25,458.96
of which cohesion funds
€ 25,458.96
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 25458.96 | 25458.96 | 100 |
State of progress
Completed
Expected start: 16/09/2019
Effective start: 16/09/2019
Expected end: 16/10/2019
Effective end: 16/10/2019
Entities
- Planning body
- COMUNE DI CASALETTO DI SOPRA
- Implementing body
- COMUNE DI CASALETTO DI SOPRA
- Beneficiary
- COMUNE DI CASALETTO DI SOPRA
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 25,458.96
- Payments on cohesion funds
- € 25,458.96
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same type of investment
EFFICIENTAMENTO SCUOLA DELL'INFANZIA | € 14,029 |