CUP: F82J19003930001
EFFICIENTAMENTO ENERGETICO MUNICIPIO PARTE 1
SUMMARY OF THE PROJECT
EFFICIENTAMENTO ENERGETICO MUNICIPIO PARTE 1
Implementation indicator
Numero di edifici pubblici o strutture oggetto di intervento
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 21,353.58
of which cohesion funds
€ 21,353.58
Given name | Amount |
---|---|
Development and Cohesion Fund | 21353.58 |
- Economies:
- € 448.08
Payments monitored
€ 21,003.62
of which cohesion funds
€ 21,003.62
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 21003.62 | 21003.62 | 98 |
State of progress
Completed
Expected start: 31/10/2019
Effective start: 31/10/2019
Expected end: 31/01/2020
Effective end: 12/11/2020
Entities
- Planning body
- COMUNE DI CARRODANO
- Implementing body
- COMUNE DI CARRODANO
- Beneficiary
- COMUNE DI CARRODANO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
SPESE DI COORDINAMENTO E MONITORAGGIO | € 229,000 |
SPESE DI COORDINAMENTO E MONITORAGGIO LOTTI INTEGRATIVI | € 13,800 |