CUP: H42C19000280005
EFFICIENTAMENTO ENERGETICO PALAZZO COMUNALE CON IMPIANTO FTV E ISOLAMENTO TERMICO SOTTOTETTO, INSTALLAZIONE POMPA DI CALORE INVERTER PER RISCALDAMENTO UFFICI
SUMMARY OF THE PROJECT
EFFICIENTAMENTO ENERGETICO PALAZZO COMUNALE - ANNO 2019
Implementation indicator
Numero di edifici pubblici con classificazione del consumo energetico migliorata
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 49,904.00
of which cohesion funds
€ 49,904.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 49904.00 |
- Economies:
- € 96.00
Payments monitored
€ 49,904.00
of which cohesion funds
€ 49,904.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 49904.00 | 49904.00 | 100 |
State of progress
Completed
Expected start: 28/10/2019
Effective start: 28/10/2019
Expected end: 29/02/2020
Effective end: 29/02/2020
Entities
- Planning body
- COMUNE DI CARAVONICA
- Implementing body
- COMUNE DI CARAVONICA
- Beneficiary
- COMUNE DI CARAVONICA
- Executor
-
SINERGY TECNOIMPIANTI
IMPRESA EDILE MASSA F.LLI SNC
EDILLEGNO DI GABBI ROBERTO E C.
CLIMASERVICE
CLEMENZI ALESSANDRO
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 49,904.00
- Payments on cohesion funds
- € 49,904.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same type of investment
Strada di collegamento intercomunale fra l'abitato di Caravonica capoluogo con Comune di Cesio tramite collegamento diretto co S.S. 28 | € 240,175 |