CUP: E85D19000210005
SOSTITUZIONE DELL'IMPIANTO CLIMATIZZAZIONE INVERNALE/ESTIVO A SERVIZIO DEL PALAZZO COMUNALE CON TECNOLOGIE AD ALTA EFFICIENZA
SUMMARY OF THE PROJECT
SOSTITUZIONE DELL'IMPIANTO CLIMATIZZAZIONE INVERNALE/ESTIVO A SERVIZIO DEL PALAZZO COMUNALE CON TECNOLOGIE AD ALTA EFFICIENZA
Implementation indicator
Numero di edifici pubblici con classificazione del consumo energetico migliorata
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 80,000.00
of which cohesion funds
€ 50,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 50000.00 |
Municipality | 30000.00 |
Payments monitored
€ 69,630.00
of which cohesion funds
€ 50,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 69630.00 | 69630.00 | 87 |
State of progress
Open
Expected start: 10/02/2020
Effective start: 10/02/2020
Expected end: 23/06/2020
Effective end: 23/06/2020
Type
- Infrastructure
- MANUTENZIONE STRAORDINARIA PER ACCESSIBILITA' E ABBATTIMENTO DELLE BARRIERE ARCHITETTONICHE
Theme
Territory
Entities
- Planning body
- COMUNE DI CAPOLIVERI
- Beneficiary
- COMUNE DI CAPOLIVERI
- Executor
- COMUNE DI CAPOLIVERI
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile