CUP: G22J19000800001
D.L. N. 34/2019 - EFFICIENTAMENTO ENERGETICO MEDIANTE INSTALLAZIONE IMPIANTO SOLARE E RISTRUTTURAZIONE IMPIANTI
SUMMARY OF THE PROJECT
INSTALLAZIONE IMPIANTO SOLARE E RISTRUTTURAZIONE IMPIANTI STABILI COMUNALI
Implementation indicator
Numero di edifici pubblici o strutture oggetto di intervento
- Target
- 4 num
- Achieved
- 4 num
Download project
Funding monitored
€ 51,593.30
of which cohesion funds
€ 50,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 50000.00 |
Municipality | 1593.30 |
Payments monitored
€ 51,593.30
of which cohesion funds
€ 50,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 51593.30 | 51593.30 | 100 |
State of progress
Completed
Expected start: 24/10/2019
Effective start: 24/10/2019
Expected end: 22/05/2020
Effective end: 05/06/2020
Entities
- Planning body
- COMUNE DI CANALE D'AGORDO
- Beneficiary
- COMUNE DI CANALE D'AGORDO
- Executor
- TERMO IDRAULICA AGORDINA S.R.L.
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 50,000.00
- Payments on cohesion funds
- € 50,000.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile