CUP: I79E19000460001
LAVORI DI RIFACIMENTO MURO DI RECINZIONE SCUOLA MEDIA DI VIA VITTORIO VENETO PROSPICIENTE L¿ORATORIO
SUMMARY OF THE PROJECT
LAVORI DI RIFACIMENTO MURO DI RECINZIONE
Implementation indicator
Interventi per la messa in sicurezza degli edifici scolastici
- Target
- 100 num
- Achieved
- 100 num
Download project
Funding monitored
€ 39,000.00
of which cohesion funds
€ 39,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 39000.00 |
Payments monitored
€ 38,932.89
of which cohesion funds
€ 38,932.89
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 38308.97 | 38308.97 | 98 |
2020 | 623.92 | 38932.89 | 99 |
State of progress
Completed
Expected start: 07/10/2019
Effective start: 07/10/2019
Expected end: 02/11/2019
Effective end: 30/10/2019
Entities
- Planning body
- COMUNE DI CAIRATE
- Beneficiary
- COMUNE DI CAIRATE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile