CUP: B92G19000170001
RIQUALIFICAZIONE ENERGETICA CENTRALE TERMICA ESISTENTE A GASOLIO DELLA SCUOLA ELEMENTARE-MATERNA, CON NUOVO GENERATORE A GAS METANO, PER IL RISCALDAMENTO DELL'EDIFICIO
SUMMARY OF THE PROJECT
RIQUALIFICAZIONE ENERGETICA DELLA CENTRALE TERMICA ESISTENTE A GASOLIO DELLA SCUOLA MATERNA E ELEMENTARE MONTANO MONTINI, CON UN NUOVO GENERATORE FUNZIONANTE A GAS METANO, PER IL SERVIZIO DELL'IMPIANTO DI RISCALDAMENTO DELL'EDIFICIO.
Implementation indicator
Numero di edifici pubblici con classificazione del consumo energetico migliorata
- Target
- 1 num
- Achieved
- 1 num
Funding monitored
€ 49,217.19
of which cohesion funds
€ 49,217.19
Given name | Amount |
---|---|
Development and Cohesion Fund | 49217.19 |
- Economies:
- € 782.81
Payments monitored
€ 49,191.47
of which cohesion funds
€ 49,191.47
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 49191.47 | 49191.47 | 99 |
State of progress
Completed
Expected start: 25/10/2019
Effective start: 30/10/2019
Expected end: 27/01/2020
Effective end: 08/01/2020
Entities
- Planning body
- COMUNE DI BRIONE
- Beneficiary
- COMUNE DI BRIONE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile