CUP: J85C19000050005
REALIZZAZIONE IMPIANTO FOTOVOLTAICO PRESSO CENTRO RACCOLTA RIFIUTI
SUMMARY OF THE PROJECT
REALIZZAZIONE IMPIANTO FOTOVOLTAICO PRESSO CENTRO RACCOLTA RIFIUTI
Implementation indicator
Numero di edifici pubblici o strutture oggetto di intervento
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 28,653.91
of which cohesion funds
€ 28,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 28000.00 |
Municipality | 653.91 |
- Economies:
- € 3,346.09
Payments monitored
€ 28,653.90
of which cohesion funds
€ 27,999.99
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 3172.00 | 3172.00 | 11 |
2020 | 25481.90 | 28653.90 | 99 |
State of progress
Completed
Expected start: 30/10/2019
Effective start: 22/07/2020
Expected end: 30/06/2020
Effective end: 27/08/2020
Entities
- Planning body
- COMUNE DI BREGNANO
- Beneficiary
- COMUNE DI BREGNANO
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 28,000.00
- Payments on cohesion funds
- € 27,999.99
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same type of investment
OPERE DI EFFICIENTAMENTO ENERGETICO IMPIANTO TERMICO MUNICIPIO,ARCHIVIO,BIBLIOTECA | € 47,343 |