CUP: D82J19000170004
LAVORI DI EFFICIENTAMENTO ENERGETICO. REALIZZAZIONE NUOVE TORRI FARO PRESSO IL CAMPO SPORTIVO DI BORGOLAVEZZARO
SUMMARY OF THE PROJECT
REALIZZAZIONE NUOVE TORRI FARO CAMPO SPORTIVO
Implementation indicator
Numero di edifici pubblici con classificazione del consumo energetico migliorata
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 111,483.03
of which cohesion funds
€ 50,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 50000.00 |
Municipality | 61483.03 |
- Economies:
- € 3,516.97
Payments monitored
€ 50,000.00
of which cohesion funds
€ 50,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 50000.00 | 50000.00 | 44 |
State of progress
Open
Expected start: 30/12/2019
Effective start: 19/05/2020
Expected end: 19/02/2020
Effective end: 30/06/2020
Entities
- Planning body
- RUP - ARCH. VALERIA GATTI
- Implementing body
- COMUNE DI BORGOLAVEZZARO
- Beneficiary
- COMUNE DI BORGOLAVEZZARO
- Executor
-
STUDIO TECNICO DELTA DI NOVARA
SPORTGYM SRLS DI BOLOGNA
FRATUS EDILE SRL DI CHIUDUNO (BG)
CORUS S.R.L. DI BERGAMO
BERARDI GIARDINI SRL DI NOVARA
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 50,000.00
- Payments on cohesion funds
- € 50,000.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis