CUP: B31C19000150001
INTERVENTI DI MESSA IN SICUREZZA E RIQUALIFICAZIONE ENERGETICA DELL¿IMPIANTO DI PUBBLICA ILLUMINAZIONE ¿ 2° LOTTO
SUMMARY OF THE PROJECT
1) RIQUALIFICAZIONE ENERGETICA DELL'IMPIANTO DI PUBBLICA ILLUMINAZIONE ATTRAVERSO LA CONVERSIONE DELLA STESSA ALLE PIù RECENTI TECNOLOGIE A LED; 2) MESSA IN SICUREZZA DELL'IMPIANTO ATTRAVERSO IL RIFACIMENTO DEI QUADRI ELETTRICI.
Implementation indicator
Riduzione dei consumi annui di energia elettrica per illuminazione pubblica
- Target
- 0.25 GWh
- Achieved
- 0.20 GWh
Download project
Funding monitored
€ 49,445.96
of which cohesion funds
€ 49,445.96
Given name | Amount |
---|---|
Development and Cohesion Fund | 49445.96 |
- Economies:
- € 554.04
Payments monitored
€ 25,000.00
of which cohesion funds
€ 25,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 25000.00 | 25000.00 | 50 |
State of progress
Open
Expected start: 28/10/2019
Effective start: 28/10/2019
Expected end: 26/12/2019
Effective end: 15/05/2020
Entities
- Planning body
- COMUNE DI BELLOSGUARDO
- Beneficiary
- COMUNE DI BELLOSGUARDO
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 49,445.96
- Payments on cohesion funds
- € 25,000.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile