CUP: C73B19000290001
LAVORI DI REALIZZAZIONE DI UN IMPIANTO FOTOVOLTAICO CONNESSO IN RETE DI POTENZA NOMINALE PARI A 10KW DA ISTALLARE SULLA COPERTURA DEGLI SPOGLIATOI DEGLI IMPIANTI SPORTIVI
SUMMARY OF THE PROJECT
LAVORI DI REALZZAZIONE IMPANTO FOTOVOLTAICO DI POTENZA PARI A 10KW A SERVIZIO DEGLI IMPIANTI SPORTIVI
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 10,000 KWh/a
- Achieved
- 10,000 KWh/a
Download project
Funding monitored
€ 13,591.87
of which cohesion funds
€ 13,591.87
Given name | Amount |
---|---|
Development and Cohesion Fund | 13591.87 |
Payments monitored
€ 5,882.67
of which cohesion funds
€ 5,882.67
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 5882.67 | 5882.67 | 43 |
State of progress
Open
Expected start: 19/12/2019
Effective start: 19/12/2019
Expected end: 19/03/2020
Effective end: 01/06/2020
Entities
- Planning body
- COMUNE DI BAUCINA
- Implementing body
- COMUNE DI BAUCINA
- Beneficiary
- COMUNE DI BAUCINA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile