CUP: B17H19002510001
INTERVENTO DI MESSA IN SICUREZZA MARCIAPIEDI
SUMMARY OF THE PROJECT
MESSA IN SICUREZZA MARCIAPIEDI DI VIA GALANTI, VIA LUZZAGO E VIA SAN MICHELE
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1 km
- Achieved
- 1 km
Download project
Funding monitored
€ 48,524.71
of which cohesion funds
€ 48,524.71
Given name | Amount |
---|---|
Development and Cohesion Fund | 48524.71 |
- Economies:
- € 1,475.29
Payments monitored
€ 48,448.81
of which cohesion funds
€ 48,448.81
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 48448.81 | 48448.81 | 99 |
State of progress
Completed
Expected start: 30/10/2019
Effective start: 30/10/2019
Expected end: 30/12/2019
Effective end: 30/09/2020
Type
- Infrastructure
- MANUTENZIONE STRAORDINARIA PER ACCESSIBILITA' E ABBATTIMENTO DELLE BARRIERE ARCHITETTONICHE
Theme
Territory
Entities
- Planning body
- COMUNE DI BASSANO BRESCIANO
- Implementing body
- COMUNE DI BASSANO BRESCIANO
- Beneficiary
- COMUNE DI BASSANO BRESCIANO
- Executor
- COMUNE DI BASSANO BRESCIANO
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 48,524.71
- Payments on cohesion funds
- € 48,448.81
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile