CUP: I99E19000630001
RIQUALIFICAZIONE DEL COMPLESSO SPORTIVO DELL¿I.C.S. ANNA BALDINO SITO IN BARANO D¿ISCHIA ALLA VIA VITTORIO EMANUELE III
SUMMARY OF THE PROJECT
LAVORI DI RIQUALIFICAZIONE DEL COMPLESSO SPORTIVO
Implementation indicator
Numero di edifici pubblici o strutture oggetto di intervento
- Target
- 2 num
- Achieved
- 2 num
Download project
Funding monitored
€ 85,186.55
of which cohesion funds
€ 85,186.55
Given name | Amount |
---|---|
Development and Cohesion Fund | 85186.55 |
- Economies:
- € 4,813.45
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Not started
Expected start: 29/10/2019
Effective start: 29/10/2019
Expected end: 27/01/2020
Effective end: 11/03/2020
Entities
- Planning body
- COMUNE DI BARANO D'ISCHIA
- Beneficiary
- COMUNE DI BARANO D'ISCHIA
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 85,186.55
- Payments on cohesion funds
- € 0.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
LAVORI DI EFFICIENTAMENTO ENERGETICO | € 1,314,194 |
IMPIANTI PER LA PRODUZIONE DI ENERGIA RINNOVABILE | € 152,977 |
GRENNYEP - IN TEMPO PER IL FUTURO | € 80,000 |
INFORMA........SCUOLA | € 75,000 |
ICT ED INNOV@ZIONE DIDATTICA | € 74,981 |
Same type of investment
MESSA IN SICUREZZA DELLA RETE STRADALE SUL TERRITORIO COMUNALE | € 979,952 |
MANUTENZIONE ORDINARIA E STRAORDINARIA DELL'EDIFICIO SCOLASTICO PLESSO TESTACCIO SITO ALLA VIA CROCE TESTACCIO | € 41,447 |