CUP: B61B19000690001
LAVORI DI EFFICIENTAMENTO ENERGETICO DELLA SCUOLA ELEMENTARE A. MORO E LOCALI VIGILI URBANIR LA MESSA IN SICUREZZA DI ALCUNE STRADE DEL PATRIMONIO COMUNALE
SUMMARY OF THE PROJECT
EFFICIENTAMENTO ENERGETICO
Implementation indicator
Numero di edifici pubblici o strutture oggetto di intervento
- Target
- 2 num
- Achieved
- 2 num
Download project
Funding monitored
€ 20,187.09
of which cohesion funds
€ 20,187.09
Given name | Amount |
---|---|
Development and Cohesion Fund | 20187.09 |
- Economies:
- € 812.91
Payments monitored
€ 20,187.09
of which cohesion funds
€ 20,187.09
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 20187.09 | 20187.09 | 100 |
State of progress
Completed
Expected start: 12/12/2019
Effective start: 12/12/2019
Expected end: 10/05/2020
Effective end: 04/03/2020
Entities
- Planning body
- COMUNE DI BALESTRATE
- Beneficiary
- COMUNE DI BALESTRATE
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 20,187.09
- Payments on cohesion funds
- € 20,187.09
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile