CUP: E52J19002480002
EFFICIENTAMENTO ENERGETICO CENTRALE TERMICA PALAZZO COMUNALE
SUMMARY OF THE PROJECT
EFFICIENTAMENTO ENERGETICO CENTRALE TERMICA PALAZZO COMUNALE
Implementation indicator
Numero di edifici pubblici o strutture oggetto di intervento
- Target
- 1 num
- Achieved
- 1 num
Funding monitored
€ 49,477.58
of which cohesion funds
€ 49,477.58
Given name | Amount |
---|---|
Development and Cohesion Fund | 49477.58 |
- Economies:
- € 522.42
Payments monitored
€ 49,477.58
of which cohesion funds
€ 49,477.58
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 4440.80 | 4440.80 | 8 |
2020 | 45036.78 | 49477.58 | 100 |
State of progress
Completed
Expected start: 29/10/2019
Effective start: 29/10/2019
Expected end: 31/12/2020
Effective end: 30/06/2020
Entities
- Planning body
- COMUNE DI BAIRO
- Beneficiary
- COMUNE DI BAIRO
- Executor
- TRUFFA IMPIANTI S.R.L.
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile