CUP: J33H19001010001
REALIZZAZIONE IMPIANTO FOTOVOLTAICO SCUOLA PRIMARIA DON BOSCO
SUMMARY OF THE PROJECT
REALIZZAZIONE DI UN IMPIANTO FOTOVOLTAICO DI 19 KW
Implementation indicator
Potenza installata
- Target
- 19 KW
- Achieved
- 19.20 KW
Download project
Funding monitored
€ 33,550.00
of which cohesion funds
€ 33,550.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 33550.00 |
Payments monitored
€ 33,550.00
of which cohesion funds
€ 33,550.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 26840.00 | 26840.00 | 80 |
2020 | 6710.00 | 33550.00 | 100 |
State of progress
Completed
Expected start: 16/10/2019
Effective start: 16/10/2019
Expected end: 14/01/2020
Effective end: 23/12/2019
Entities
- Planning body
- COMUNE DI AVEZZANO
- Beneficiary
- COMUNE DI AVEZZANO
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 33,550.00
- Payments on cohesion funds
- € 33,550.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile