CUP: H81C19000060001
LAVORI DI EFFICIENTAMENTO ENERGETICO MEDIANTE RELAMPING DEGLI IMPIANTI DI P.I.
SUMMARY OF THE PROJECT
EFFICIENTAMENTO ENERGETICO MEDIANTE RELAMPING DEGLI IMPIANTI DI PUBBLICA ILLUMINAZIONE A SERVIZIO DEL CAMPO SPORTIVO COMUNALE ED INSTALLAZIONE DI NUOVO IMPIANTO DI PUBBLICA ILLUMINAZIONE A TECNOLOGIA LED TRA VIA SAN VITO E L'ABBADIA DI SAN VITO
Implementation indicator
Punti illuminanti/luce
- Target
- 20 num
- Achieved
- 20 num
Download project
Funding monitored
€ 50,000.00
of which cohesion funds
€ 50,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 50000.00 |
Payments monitored
€ 25,000.00
of which cohesion funds
€ 25,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 25000.00 | 25000.00 | 50 |
State of progress
Open
Expected start: 21/10/2019
Effective start: 26/10/2019
Expected end: 25/05/2020
Effective end: 10/03/2020
Entities
- Planning body
- COMUNE DI AQUILONIA
- Beneficiary
- COMUNE DI AQUILONIA
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 50,000.00
- Payments on cohesion funds
- € 25,000.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile