CUP: J49J21015190007
RIFACIMENTO IMPIANTO DI ILLUMINAZIONE ALL'INTERNO DELLA 2 GALLERIA VIA FERROVIA EST
SUMMARY OF THE PROJECT
RIFACIMENTO IMPIANTO DI ILLUMINAZIONE ALL'INTERNO DELLA 2 GALLERIA VIA FERROVIA EST
Implementation indicator
Punti illuminanti/luce
- Target
- 5 num
- Achieved
- 5 num
Download project
Funding monitored
€ 3,390.95
of which cohesion funds
€ 3,390.95
Given name | Amount |
---|---|
Development and Cohesion Fund | 3390.95 |
- Economies:
- € 533.10
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 05/04/2021
Effective start: 05/04/2021
Expected end: 06/04/2022
Effective end: 06/04/2022
Entities
- Planning body
- COMUNE DI ALTOFONTE
- Beneficiary
- COMUNE DI ALTOFONTE
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 3,390.95
- Payments on cohesion funds
- € 0.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile