CUP: J44H20001290001
RIFACIMENTO TRATTI RETE IDRICA IN VIA FERROVIA OVEST
SUMMARY OF THE PROJECT
TRATTI RETE IDRICA
Implementation indicator
Reti
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 24,268.98
of which cohesion funds
€ 24,268.98
Given name | Amount |
---|---|
Development and Cohesion Fund | 24268.98 |
- Economies:
- € 7,572.71
Payments monitored
€ 23,666.42
of which cohesion funds
€ 23,666.42
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 23666.42 | 23666.42 | 97 |
State of progress
Completed
Expected start: 10/11/2020
Effective start: 10/11/2020
Expected end: 30/12/2020
Effective end: 17/12/2020
Entities
- Planning body
- COMUNE DI ALTOFONTE
- Implementing body
- COMUNE DI ALTOFONTE
- Beneficiary
- COMUNE DI ALTOFONTE
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 24,268.98
- Payments on cohesion funds
- € 23,666.42
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile