CUP: F67H19002400001
ADEGUAMENTO E MESSA IN SICUREZZA DELLA STRADA COMUNALE VALLE SCURO
SUMMARY OF THE PROJECT
ADEGUAMENTO E MESSA IN SICUREZZA DELLA STRADA
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 0.50 km
- Achieved
- 0.40 km
Download project
Funding monitored
€ 38,945.58
of which cohesion funds
€ 38,945.58
Given name | Amount |
---|---|
Development and Cohesion Fund | 38945.58 |
- Economies:
- € 11,054.42
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Not started
Expected start: 23/10/2019
Effective start: 23/10/2019
Expected end: 31/01/2020
Effective end: 07/02/2020
Entities
- Planning body
- COMUNE DI ALTAVILLA IRPINA
- Beneficiary
- COMUNE DI ALTAVILLA IRPINA
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 38,945.58
- Payments on cohesion funds
- € 0.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile