CUP: D92J19000450001
SOSTITUZIONE SERRAMENTI MUNICIPIO
SUMMARY OF THE PROJECT
Sostituzione delle finestre da legno in alluminio del palazzo municipale
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 3,771 KWh/a
- Achieved
- 3,771 KWh/a
Download project
Funding monitored
€ 21,020.60
of which cohesion funds
€ 21,020.60
Given name | Amount |
---|---|
Development and Cohesion Fund | 21020.60 |
Payments monitored
€ 21,020.60
of which cohesion funds
€ 21,020.60
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 21020.60 | 21020.60 | 100 |
State of progress
Completed
Expected start: 21/10/2019
Effective start: 21/10/2019
Expected end: 31/12/2019
Effective end: 21/02/2020
Entities
- Planning body
- COMUNE DI ALAGNA
- Beneficiary
- COMUNE DI ALAGNA
- Executor
- R.E.D. snc di Roda Renato e Donati Pierangelo
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 21,020.60
- Payments on cohesion funds
- € 21,020.60
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile