CUP: C52I19000360001
Lavori di Relamping di via Regina Margherita
SUMMARY OF THE PROJECT
Lavori di Relamping di via Regina Margherita
Implementation indicator
Riduzione annuale del consumo di energia
- Target
- 21.68 MW
- Achieved
- 36.98 MW
Download project
Funding monitored
€ 22,773.53
of which cohesion funds
€ 22,773.53
Given name | Amount |
---|---|
Development and Cohesion Fund | 22773.53 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 03/08/2020
Effective start: 04/10/2021
Expected end: 31/12/2020
Effective end: 11/11/2021
Entities
- Planning body
- COMUNE DI ACI SANT'ANTONIO
- Beneficiary
- COMUNE DI ACI SANT'ANTONIO
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 22,773.53
- Payments on cohesion funds
- € 0.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
Same type of investment
Sostituzione dell'illuminazione esterna Villa Comunale - Relamping | € 67,226 |