CUP: D79D14000110006
Interventi di efficientamento dell'impianto di illuminazione pubblica
Download project
Funding monitored
€ 82,037.79
of which cohesion funds
€ 82,037.79
Given name | Amount |
---|---|
European Union | 26252.09 |
Revolving Fund (National co-financing) | 33225.31 |
Region | 3691.70 |
Municipality | 18868.69 |
Payments monitored
€ 82,037.79
of which cohesion funds
€ 82,037.79
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 82037.79 | 82037.79 | 100 |
State of progress
Completed
Expected start: 02/01/2015
Effective start: 23/03/2015
Expected end: 27/02/2015
Effective end: 20/04/2015
Type
- Infrastructure
- MANUTENZIONE STRAORDINARIA
Theme
- Energy
- Efficienza dell'energia, cogenerazione, gestione dell'energia
Territory
Entities
- Planning body
- REGIONE AUTONOMA FRIULI-VENEZIA GIULIA
- Implementing body
- COMUNE DI GONARS
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Promuovere le opportunità di sviluppo locale attraverso l'attivazione di filiere produttive collegate all'aumento della quota di energia prodotta da fonti rinnovabili e al risparmio energetico
- Specific objective QSN
- Promozione dell'efficienza energetica e del risparmio dell'energia
Programming area
- Programme
- ROP RCE ERDF FRIULI VENEZIA GIULIA
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Cohesion funds
- € 82,037.79
- Payments on cohesion funds
- € 82,037.79
- Axis
- ASSE 5 - ECOSOSTENIBILITA' ED EFFIC.ENERGETICA DEL SIST.PROD
- Operational objective
- Sostenere l'efficienza energetica e l'utilizzo delle fonti rinnovabili.