CUP: B43D15000350006
IMPIANTO FOTOVOLTAICO DA 19,32 KWP SU COPERTURA A TERRAZZA
Download project
Funding monitored
€ 15,460.00
of which cohesion funds
€ 15,460.00
Given name | Amount |
---|---|
European Union | 4947.20 |
Revolving Fund (National co-financing) | 6261.30 |
Region | 4251.50 |
- Other resources - Private:
- € 61,840
Payments monitored
€ 15,460.00
of which cohesion funds
€ 15,460.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 15460.00 | 15460.00 | 100 |
State of progress
Completed
Expected start: 24/09/2010
Effective start: 24/09/2010
Expected end: 30/11/2010
Effective end: 30/11/2010
Type
- Incentives for firms
- ALTRO
Theme
- Energy
- Efficienza dell'energia, cogenerazione, gestione dell'energia
Territory
Entities
- Planning body
- CAMERA DI COMMERCIO INDUSTRIA ARTIGIANATO E AGRICOLTURA DI PORDENONE
- Implementing body
- MARA SRL
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Promuovere le opportunità di sviluppo locale attraverso l'attivazione di filiere produttive collegate all'aumento della quota di energia prodotta da fonti rinnovabili e al risparmio energetico
- Specific objective QSN
- Diversificazione delle fonti energetiche e aumento dell'energia prodotta da fonti rinnovabili
Programming area
- Programme
- ROP RCE ERDF FRIULI VENEZIA GIULIA
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Cohesion funds
- € 15,460.00
- Payments on cohesion funds
- € 15,460.00
- Axis
- ASSE 5 - ECOSOSTENIBILITA' ED EFFIC.ENERGETICA DEL SIST.PROD
- Operational objective
- Sostenere l'efficienza energetica e l'utilizzo delle fonti rinnovabili.