CUP: H17H18000800002
ADEGUAMENTO E MESSA IN SICUREZZA SP 67 BARAGIANO SCALO - S. ANTONIO CASALINI (BELLA)
SUMMARY OF THE PROJECT
REGIMENTAZIONE DELLE ACQUE METEORICHE (ZANELLE, POZZETTI, TOMBINI) - RIFACIMENTO PIANO VIABILE - INTEGRAZIONE BARRIERE
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 2.50 km
- Achieved
- 2.25 km
Download project
Funding monitored
€ 267,301.99
of which cohesion funds
€ 267,301.99
Given name | Amount |
---|---|
European Union | 200476.49 |
Revolving Fund | 46777.85 |
Region | 20047.65 |
- Economies:
- € 132,698.01
Payments monitored
€ 267,301.99
of which cohesion funds
€ 267,301.99
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 225.00 | 225.00 | 0 |
2020 | 267076.99 | 267301.99 | 100 |
State of progress
Completed
Expected start: 04/03/2020
Effective start: 04/03/2020
Expected end: 03/07/2020
Effective end: 03/07/2020
Entities
- Planning body
- REGIONE BASILICATA
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI POTENZA
- Beneficiary
- AMMINISTRAZIONE PROVINCIALE DI POTENZA
- Executor
-
GEOPROTECTION S.R.L.
C. COSTRUZIONI S.R.L.
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- ROP ERDF BASILICATA
- Axis
- Sistemi di trasporto ed infrastrutture di rete
- Specific objective
- Rafforzamento delle connessioni dei nodi secondari e terziari della rete TEN-T