CUP: E47H18001570002
INTERVENTO BARAGIANO ""VIALE DEI PINI"" E ""EX SS7 BARAGIANO SCALO""
SUMMARY OF THE PROJECT
LAVORI DI PAVIMENTAZIONE STRADALE, CANALIZZAZIONE E RACCOLTA ACQUE METEORICHE
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1.50 km
- Achieved
- 1.50 km
Funding monitored
€ 474,673.05
of which cohesion funds
€ 474,673.04
Given name | Amount |
---|---|
European Union | 241607.74 |
Revolving Fund | 158250.02 |
Region | 74815.29 |
- Economies:
- € 25,326.96
Payments monitored
€ 322,143.65
of which cohesion funds
€ 322,143.65
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 24439.11 | 24439.11 | 5 |
2020 | 0 | 24439.11 | 5 |
2021 | 0 | 24439.11 | 5 |
2022 | 2206.13 | 26645.24 | 5 |
2023 | 295498.41 | 322143.65 | 67 |
State of progress
Open
Expected start: 18/09/2023
Effective start: 18/09/2023
Expected end: 08/02/2024
Effective end: 08/02/2024
Entities
- Planning body
- REGIONE BASILICATA
- Implementing body
- COMUNE DI BARAGIANO
- Beneficiary
- COMUNE DI BARAGIANO
- Executor
- COMUNE DI BARAGIANO
Programming area
- 2014-2020 Cohesion Action Plan
- 2014-2020 Cohesion Action Plan
- Programme
- POC BASILICATA
- CAP area axis
- Sistemi di trasporto ed infrastrutture di rete
- CAP action line
- RAFFORZARE LE CONNESSIONI DEI NODI SECONDARI E TERZIARI DELLE ÂAREE INTERNEÂ E DI QUELLE DOVE SONO LOCALIZZATI SIGNIFICATIVI DISTRETTI DI PRODUZIONE AGRICOLA E AGRO INDUSTRIALE CON I PRINCIPALI ASSI
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- ROP ERDF BASILICATA
- Axis
- Sistemi di trasporto ed infrastrutture di rete
- Specific objective
- Rafforzamento delle connessioni dei nodi secondari e terziari della rete TEN-T