CUP: H27H18000180002
PROVINCIALE EX SS 103 TRATTO LIMITE DI PROVINCIA - BIVIO CIRIGLIANO KM 9 (RELAZIONE GORGOGLIONE - STIGLIANO; POTENZA; MATERA; POLICORO)
SUMMARY OF THE PROJECT
LAVORI DI MANUTENZIONE STRAORDINARIA: RIPRISTINO TRATTI NON PI PERCORRIBILI.
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 2.50 km
- Achieved
- 0.10 km
Download project
Funding monitored
€ 500,000.00
of which cohesion funds
€ 500,000.00
Given name | Amount |
---|---|
European Union | 375000.00 |
Revolving Fund | 87500.00 |
Region | 37500.00 |
Payments monitored
€ 460,306.40
of which cohesion funds
€ 460,306.40
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 19910.49 | 19910.49 | 3 |
2022 | 8924.34 | 28834.83 | 5 |
2023 | 414922.00 | 443756.83 | 88 |
2024 | 16549.57 | 460306.40 | 92 |
State of progress
Open
Expected start: 20/10/2022
Effective start: 20/10/2022
Expected end: 31/10/2023
Effective end: 07/07/2023
Entities
- Planning body
- REGIONE BASILICATA
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI MATERA
- Beneficiary
- AMMINISTRAZIONE PROVINCIALE DI MATERA
- Executor
- AMMINISTRAZIONE PROVINCIALE DI MATERA
Programming area
- Programme
- ROP ERDF BASILICATA
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 500,000.00
- Payments on cohesion funds
- € 460,306.40
- Axis
- Sistemi di trasporto ed infrastrutture di rete
- Specific objective
- Rafforzamento delle connessioni dei nodi secondari e terziari della rete TEN-T
Internal Areas
Other projects in territory
Same theme
Same type of investment
VIE BLU - STRALCIO ESECUTIVO 2010 | € 12,597,951 |
VIE BLU - STRALCIO ESECUTIVO 2008 | € 12,553,078 |
VIE BLU - STRALCIO ESECUTIVO 2009 | € 12,103,131 |
VIE BLU - STRALCIO ESECUTIVO 2015 | € 4,845,000 |
MURGIA - POLLINO: COLLEGAMENTO MEDIANO MURGIA - POLLINO MATERA - FERRANDINA Â PISTICCI (STRALCIO) | € 4,800,000 |