CUP: H67H18000330002
STRADA PROVINCIALE EX 103 (RELAZIONE CIRIGLIANO-STIGLIANO)
SUMMARY OF THE PROJECT
LAVORI DI MANUTENZIONE STRAORDINARIA
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1 km
- Achieved
- 1 km
Download project
Funding monitored
€ 150,000.00
of which cohesion funds
€ 150,000.00
Given name | Amount |
---|---|
European Union | 112500.00 |
Revolving Fund | 26250.00 |
Region | 11250.00 |
Payments monitored
€ 134,639.50
of which cohesion funds
€ 134,639.50
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 5274.15 | 5274.15 | 3 |
2020 | 129365.35 | 134639.50 | 89 |
State of progress
Open
Expected start: 06/11/2019
Effective start: 06/11/2019
Expected end: 22/11/2019
Effective end: 22/11/2019
Entities
- Planning body
- REGIONE BASILICATA
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI MATERA
- Beneficiary
- AMMINISTRAZIONE PROVINCIALE DI MATERA
- Executor
- SERRA DIONISIO
Programming area
- Programme
- ROP ERDF BASILICATA
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 150,000.00
- Payments on cohesion funds
- € 134,639.50
- Axis
- Sistemi di trasporto ed infrastrutture di rete
- Specific objective
- Rafforzamento delle connessioni dei nodi secondari e terziari della rete TEN-T