CUP: H21B21000480006
EFFICIENTAMENTO ILLUMINAZIONE PUBBLICA CASTELLO, PONTE DEL PIANELLO E SENTIERO DELLE RIPE
SUMMARY OF THE PROJECT
INTERVENTO DI EFFICIENTAMENTO ILLUMINAZIONE PUBBLICA CASTELLO, PONTE DEL PIANELLO E SENTIERO DELLE RIPE
Download project
Funding monitored
€ 49,458.00
of which cohesion funds
€ 49,458.00
Given name | Amount |
---|---|
European Union | 37093.50 |
Revolving Fund | 8655.15 |
Region | 3709.35 |
- Economies:
- € 542.00
Payments monitored
€ 49,458.00
of which cohesion funds
€ 49,458.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 49458.00 | 49458.00 | 100 |
State of progress
Completed
Expected start: 03/03/2023
Effective start: 03/03/2023
Expected end: 30/04/2023
Effective end: 30/04/2023
Entities
- Planning body
- REGIONE BASILICATA
- Implementing body
- COMUNE DI MURO LUCANO
- Beneficiary
- COMUNE DI MURO LUCANO
- Executor
- COMUNE DI MURO LUCANO
Programming area
- Programme
- ROP ERDF BASILICATA
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 49,458.00
- Payments on cohesion funds
- € 49,458.00
- Axis
- Energia e mobilità urbana
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili