Updated on 31/08/2022
Funding monitored € 537,000.00 of which cohesion funds € 429,600.00
Given name Amount
Development and Cohesion Fund107400.00
Revolving Fund (Cohesion Action Plan)429600.00
Payments monitored € 537,000.00 of which cohesion funds € 429,600.00 100%
Year Amount Cumulative amount Percentage on public financing
2018277773.66277773.6651
2019259226.34537000.00100

State of progress

Completed
Expected start: 01/01/2015
Effective start: 02/01/2016
Expected end: 01/01/2015
Effective end: 28/11/2019

Type

Theme

  • Energy
  • Progetti integrati per la rigenerazione urbana e rurale

Territory

Entities

Planning body
REGIONE PIEMONTE
Implementing body
COMUNE DI ALESSANDRIA
Beneficiary
COMUNE DI ALESSANDRIA
Executor
COMUNE DI ALESSANDRIA
Priority QSN
Valorizzazione delle risorse naturali e culturali per l'attrattività e lo sviluppo
General objective QSN
Valorizzare le risorse naturali, culturali e paesaggistiche locali, trasformandole in vantaggio competitivo per aumentare l'attrattività, anche turistica, del territorio, migliorare la qualità della vita dei residenti e promuovere nuove forme di sviluppo economico sostenibile
Specific objective QSN
Valorizzare i beni e le attività culturali quale vantaggio comparato delle Regioni italiane per aumentarne l'attrattività territoriale, per rafforzare la coesione sociale e migliorare la qualità della vita dei residenti

Programming area

Programme
PROGRAMMA PAC PIEMONTE
2007-2013 Cohesion Action Plan
2007-2013 Cohesion Action Plan
Cohesion funds
€ 429,600.00
Payments on cohesion funds
€ 429,600.00
Line
Salvaguardia
Action
PISU Alessandria: illuminazione via Bruno, Dossena, C.so Monferrato e parcheggio Cittadella